The most expensive mistakes in backyard construction happen between contractors rather than within them. The hardscape crew pours a patio, the landscaper arrives three weeks later and needs an irrigation line across it, and someone saw cuts a slab that was finished eleven days earlier. Or a beautiful planting plan goes in over a drainage design that was never told about the new grade. Benitez Contractors coordinates the built and living portions of a project so the sequence is correct, the sleeves are in the ground before the concrete, and one party is accountable for the seams instead of everyone pointing at each other.
About 4 min left
What Is the Correct Sequence for a Whole Yard?
Demolition, rough grading, all underground, structures, finished surfaces, then irrigation finish, planting and lighting trim. Underground is the phase that gets compressed and it should never be, because it includes drainage lines, gas sleeves, electrical conduit, low voltage runs, irrigation mainline and lateral sleeves under every future hardscape crossing, and pool or spa plumbing if either is planned in any future phase. Structures follow because post footings need to be poured to an elevation set by the finished surface, and because building a pergola after the patio means protecting a brand new surface from a concrete mixer. Finished surfaces come next. Irrigation heads, planting and lighting go last so that fixtures and plants are not damaged by masonry work, and so that the lighting can be aimed against actual plant material rather than empty dirt. Deviating from this order always costs money somewhere.
Why Do Sleeves Matter So Much?
A sleeve is an empty conduit crossing under a hardscape surface, installed for a line that may not exist yet, and it is the cheapest insurance in backyard construction. Installing a two inch PVC sleeve under a patio during construction costs a few dollars in material and about ten minutes of labor. Retrofitting the same crossing afterward means saw cutting the slab or lifting a paver field, trenching, backfilling, compacting and repairing the surface, at a cost measured in thousands with a visible repair scar as the permanent souvenir. We install sleeves at every hardscape crossing whether or not the homeowner has committed to a future feature: one for irrigation, one for low voltage lighting, one for line voltage electrical, and one for gas where a future fire feature or kitchen is even remotely plausible. Sleeve ends are marked, capped and documented on the as built we hand over at closeout.
- Irrigation sleeves: Mainline and lateral crossings under every walkway and patio, sized larger than the pipe so future replacement is a pull, not a dig.
- Low voltage sleeves: Lighting cable crossings so future fixtures on the far side of a patio do not require lifting the surface.
- Line voltage conduit: Spare conduit for a future gazebo, spa, fountain pump or shed, installed at proper burial depth with pull string in place.
- Gas sleeves: A sleeve toward the future fire pit or kitchen location, which converts a saw cutting job into a simple pipe pull later.
How Do Drainage and Planting Design Interact?
New hardscape reduces permeable area and concentrates runoff, and where that runoff goes is usually a planting bed. A design that dumps roof and patio water into a bed planted with drought tolerant Mediterranean species is a design that kills those plants, because the two most common causes of death in a California native or Mediterranean planting are overwatering and poor drainage, not drought. The coordination work is matching the drainage plan to the planting plan: directing concentrated flow to inlets and pipe rather than into beds, using bioswales or rain gardens deliberately with species selected for periodic inundation, keeping finished soil grade below the top of adjacent hardscape so water sheets off rather than washing mulch across the patio, and setting root barriers where a tree sits close enough to hardscape that roots will eventually lift it. Trees within about five feet of a slab or paver field need a barrier as a matter of course.
What Are the Water Efficiency Requirements?
California requires landscape water efficiency compliance on qualifying projects through the Model Water Efficient Landscape Ordinance, and most Orange County cities have adopted their own version of it. In practice, rehabilitated residential landscapes above a certain area threshold trigger documentation requirements: a landscape plan, an irrigation design, a soil management report and a water budget calculation. The thresholds and the exact forms vary by city, and permit intake staff will ask for the package if the project crosses the line. Practical design responses that satisfy the intent and produce a better yard anyway include hydrozoning so plants with similar water needs share a valve, drip irrigation for all shrub and groundcover areas rather than overhead spray, a smart controller with a weather sensor, and mulch depth that actually holds moisture. We confirm the applicable threshold with your city during design rather than discovering it at permit intake.
Scope
What's Included
Everything below is written into your scope of work before construction starts. Anything outside it requires a signed change order first.
- Master schedule across all trades: One sequence covering demolition, grading, underground, structures, surfaces, irrigation, planting and lighting with dependencies mapped.
- Sleeve and conduit plan: Every hardscape crossing sleeved for irrigation, low voltage, line voltage and gas, capped, marked and documented on an as built.
- Drainage and grading coordination: Finished elevations reconciled between hardscape, planting beds and drain inlets so water leaves the property as designed.
- Trade interface management: Landscape, irrigation, masonry, electrical, gas and pool trades scheduled against each other with clear handoff points and access windows.
- Water efficiency documentation support: Applicable ordinance threshold confirmed with your city and the required landscape documentation package coordinated for submittal.
- Protection and site management: Finished surfaces protected during later phases, debris managed, and a single point of contact for access, deliveries and questions.
How it works
Our Process
Every project follows the same structured sequence, so you always know what happens next and who to call.
Scope mapping across trades
3 to 7 daysEvery element assigned to a responsible trade with the seams identified explicitly, so nothing sits in the gap between two contracts.
Sequence and dependency schedule
3 to 5 daysA working calendar built backward from the finish date with each trade dependency mapped and access windows assigned.
Underground coordination
1 to 2 weeksAll drainage, sleeves, conduit, gas and irrigation mainline installed and documented in one pass before any surface work begins.
Structure and surface phase management
2 to 6 weeksStructures and hardscape built in the right order, with inspections coordinated and finished work protected from following trades.
Planting, irrigation and lighting closeout
1 to 2 weeksPlanting and irrigation finished, lighting aimed at night against actual plant material, controllers programmed and as built documents delivered.
Budget
What does it cost?
Real ranges, stated up front. Your written proposal replaces these estimates with fixed numbers for your actual scope.
Typical range
$2,500 to $22,000
per project
Estimated 2026 Orange County pricing for coordination scope, including scheduling, sleeving, drainage reconciliation and trade management, when purchased alongside construction. On projects we build in full, coordination is typically bundled rather than billed separately. Standalone coordination on a large multi trade project sits at the upper end. Planning estimate only.
Typical timeline: Coordination runs the full length of the project, typically six to sixteen weeks for a complete backyard. The highest value window is the two weeks of underground work, where decisions made once determine what every later phase costs.
What moves the price
- Number of separate trades: Two contractors coordinate easily. Six, including a pool builder and a separate landscape designer, requires real project management hours.
- Project duration: Coordination cost scales with calendar time more than with square footage, since it is a management function rather than a material one.
- Extent of underground work: A yard with drainage, gas, electrical, low voltage, irrigation and pool plumbing all crossing each other takes far more planning than a simple patio.
- Water efficiency documentation: Projects that cross the local landscape ordinance threshold require a plan set, irrigation design, soil report and water budget calculation.
- Site access constraints: A single narrow gate shared by every trade forces sequential rather than parallel work, extending schedule and coordination effort.
- Existing landscape protection: Mature trees, established planting and finished areas that must survive construction require protection measures and careful trade routing.
Answers
Frequently asked questions
What is the right order to build a backyard?
Demolition and rough grading, then all underground work, then structures, then finished surfaces, then irrigation, planting and lighting. Underground must include sleeves for every future phase. Building out of sequence is the most common reason homeowners pay twice for the same crossing.
Why do I need sleeves under hardscape?
Because a two inch PVC sleeve costs a few dollars and ten minutes during construction, while retrofitting the same crossing later means saw cutting concrete or lifting a paver field, trenching, compacting and repairing, at a cost in the thousands with a visible permanent scar.
Can you work with my landscape designer?
Yes, and it is a common arrangement. We build the structural and hardscape portion and coordinate schedule, elevations, sleeving and drainage with the designer and the planting crew, so the seams between the built work and the living work are owned by someone rather than by no one.
What is MWELO and does it apply to my project?
The Model Water Efficient Landscape Ordinance is California landscape water efficiency law, adopted in local form by most Orange County cities. Rehabilitated residential landscapes above a certain area threshold require a landscape plan, irrigation design, soil report and water budget calculation. We confirm your city threshold during design.
How do new patios affect existing irrigation?
Almost always significantly. New hardscape typically cuts existing laterals, orphans heads and changes hydrozones, and the old spray pattern rarely fits the new bed shapes. Irrigation should be redesigned as part of the project rather than patched, and sleeves must go in before any surface is placed.
Do trees near a patio need root barriers?
Yes, generally for any tree within about five feet of a slab or paver field, and further for aggressive rooting species. A linear root barrier redirects roots downward rather than under the surface. Retrofitting one after a patio has lifted means removing hardscape and often cutting structural roots.
Next step
Get a written quote for landscape construction coordination
Book a free consultation. We walk the space, talk through what you want, and send a written scope with real numbers. No pressure and no obligation.
Licensed and insured. Written scope before work begins. Weekly progress updates with photos.
What happens next: we reply the same business day, schedule a walkthrough, then send your written proposal.